| * |
Construction
of all 132 GE Wind Energy 1.5 –megawatt wind turbines in 2007;
an additional 39, 2008 |
| * |
The
distance from ground to hub is 213 feet, which, if placed next to
the Statue of Liberty, would be slightly higher than the raised torch
on the statue. |
| * |
The
length each rotor blade is 113 feet. When raised to its highest position,
the tip of the blade would rise higher than the dome on the Iowa State
Capitol. |
| * |
The
rotor assembly weighs 48,000 pounds. |
| * |
The
turbine nacelle weighs 115,000 pounds. |
| * |
Supporting
each tower is a concrete foundation, which are 42 feet wide and eight
feet deep. |
| * |
Each
foundation contains 167 cubic yards of concrete, or equal to the contents
of more than 25 concrete-mixing trucks. Nearly 18,000 cubic yards
of concrete were needed to complete the 107 wind turbine foundations.
|
| * |
Each
foundation has 30,000 pounds of reinforcing steel. More than 3.2 million
pounds of reinforcing steel was needed to complete the 107 wind turbine
foundations. |
| * |
More
than 70 miles of three-phase underground electric line have been buried.
|
| * |
There
have been more than 225 contractors on site in November and December
of 2006. |
| * |
Contractors
have worked approximately 158,000 hours with one Occupational Safety
and Health Administration recordable accident. |
| |
Facts
about the Turbine |
| * |
Rotor
Assembly 48,000 lbs. |
| * |
Turbine
Nacella 115,000 lbs. |
| * |
Rotor
assembly for Pomeroy – 126 feet per blade |
| * |
265’
from base to the turbine Nacella |
| * |
Base
42’ x 8’ |
| * |
254
cubic yards concrete |
| * |
50’
base diameter |
| * |
58,000
lbs. of rebar |
| * |
30,000
lbs. of reinforcing steel |
| * |
167
cubic yards of concrete |
| |
|